CURRENT STATUS: Phase 2 | |
June 2019 | Sending out RFP to venders |
Timeline
An LCS Review Committee was formed to provide feedback and guide the process. The committee was co-chaired by Tim Chavis, Chief Information Officer, IT Services and Lynn Wietecha, Director eLearning Services and was comprised of:
- 利记sbo faculty representing all 利记sbo colleges and most academic programs
- Select 利记sbo administration
- 利记sbo surveyed faculty to determine critical requirements of any LMS here at 利记sbo
FACULTY SURVEYSurvey results were analyzed and results were shared with the 利记sbo community via a summary video A Request for Proposal was drafted and shared with the committee and revised several times based on suggestions and feedback. Review meetings were held on 6/1/2019 so all committee members could discuss their suggestions. The committee was informed of how their feedback was incorporated via a short summary video The final RFP was posted and shared with vendors on 6/24/2019.
The final RFP was posted and shared with vendors on 6/24/2019.
Responding vendors must include the information required in this RFP, both the LMS RFP document and the RFP Addendum. We’ve made the two files available in MS Word and Excel formats to aid completion. The two files are:
利记sbo reserves the right to reject a proposal if required information is not provided or if the proposal not organized as directed in the RFP. 利记sbo also reserves the right to change the evaluation criteria and/or any other provision in the RFP by posting notice of the change(s).
6/24/2019 - 7/8/2019 | RFP open to Vendors |
6/24/2019 - 7/8/2019 | Q&A period with Vendors. If a vendor has a question while reviewing the RFP, they can email LectureCaptureRFP@51jiyangshi.com. Answers to all questions will be provided to all vendors. |
7/8/2019 | Vendor responses due |
7/8/2019 - 7/19/2019 | Internal review of proposals |
7/22/2019 | Notify finalists |
7/22/2019 - 8/2/2019 | Onsite vendor presentations |
Vendor Presentations
|
|
7/22/2019 - 8/2/2019 | Test systems made available by finalists |
8/2019 - 9/2019 | Finalize internal testing. Vendor references will be contacted at this time. |
10/1/2019 | Preferred vendor notified. Contract negotiations begin. |
10/11/2019 | Contract awarded |